Offer letter

Footing Retrofitting Work.




Ref: FC/Offer/ft-2/19, 2017                                                                          Date: February 19, 2017


To,
Fmilytex (BD) Ltd.
Plot no-47, 48, Road -05,
Sector – 04, CEPZ,
Chittagong, Bangladesh.


For Attn.
Engineering Department



Dear Sir,

With reference to our discussion regarding the retrofitting work,  at factory building of Your Factory Premises at NLZ (BD) Ltd. We are Pleased to Submit our Technical & financial offer.


We hope that our proposal will be in line with your requirements and please do not hesitate to
 Contact us if you require any clarification.

              Thanks for your co-operation.




With Best Regard's

           

Md. Mahmudul Hasan Bhuiyan (Rana)
Managing Director
Focus Engineering & Construction
Cell: +8801818980727
Email: rana.bspi@yahoo.com
           









To,
Fmilytex (BD) Ltd.
Plot no-47, 48, Road -05,
Sector – 04, CEPZ,
Chittagong, Bangladesh.

Sub- Offer for Retrofitting works at NLZ (BD) Ltd.

Sl no
Description
unit
Quantity
Rate
Taka
1
Dismantling of RCC /CC in Floor
sft
1572.77
         100.00
              157,277.12
2
Dismantling of 5" Brick wall for Column Retrofitting
sft
798.00
           15.00
                11,970.00

Dismantling of 10" brick wall
sft
1.00
           25.00
                         25.00
3
Rubbish carry from floor to safe place inside factory Boundary
cft
995.72
             7.00
                   6,970.07
4
Earth Excavation up to 7'0''
cft
9436.63
           15.00
              141,549.41
5
Back Filing
cft
8155.47
             7.00
                57,088.26
6
Brick Flat Soling
sft
1572.77
             4.00
                   6,291.08
7
10" Brick wall for Column Retrofitting
cft
1.00
           30.00
                         30.00

5" brick wall
sft
1.00
           15.00
                         15.00
8
5" CC work in Floor with brick cheeps (1:3:6)
sft
1572.77
           55.00
                86,502.42
9
1.5" peton stone Flooring with NCF(1:1.5:3)
sft
1572.77
           15.00
                23,591.57
10
New plaster in wall & celling
sft
1.00
           15.00
                         15.00
11
RCC/ Plaster chipping in Column
sft
1949.13
             8.00
                15,593.05
12
Chemical apply in column new & old concrete bonding agent "BASF Masterbrace_1414"
sft
172.64
             5.00
                      863.20
13
10mm @ Shear connector 4" c/c, BASF
nos
2100.85
           10.00
                21,008.48
14
16, 20mm dia main bar in column
nos
672.00
           15.00
                10,080.00
15
New RCC 3/4" stone cheeps (1:1.5:3)  Works in Base/ Footing
cft
1281.16
         120.00
              153,739.37
16
New RCC 3/4" stone cheeps (1:1.5:3)  Works in Column
sft
1564.08
           80.00
              125,126.40
17
Shattering works
sft
948.55
           35.00
                33,199.35
18
MS bar
kg
7701.18
             5.00
                38,505.90
Total
        889,440.68

Eight Lac Eighty Nine Thousand Four Hundred Forty and Sixty Eight Pasha Only



Important Note:
1.       Work facilities ensure by factory authority. 
2.       Offer rate consider only service cost (without materials)
3.       Above rate 10% each above floor.

 Terms and Conditions:
1.       Scope of Work:
a.       Contractor Responsibility:
                                    i.      Contractor will maintain the quality and safety of the Works.
                                   ii.      Our scope of work is limited to complete the works as per list provided with this offer
                                 iii.      Any additional item rate will be considerate as market price.

b.      Client’s Responsibility:
                                    i.      Providing the concerned departmental personnel to ease the works.
                                  ii.      All shattering materials likes, wood, bamboo, nail, steel prof, I-joist, weir, rough provide by authority.
                                 iii.      All construction materials should be in site in due time.
                                iv.      Work place should be vacant 12 hour earlier.
                                  v.      Work plan provide by authority as their requirement.  
                                vi.      Procuring all sorts of permission and formalities from the authorities/bodies.
                               vii.      Ensuring the work environment to continue the works.
                             viii.      All excess rubbish, clay, and soil will be carried out from factory premises by Authority.   
c.       Time Line: As per our assumption the work will need 6 month maximum to complete. Contingency:
Deliverable may delayed due to following issues
·     Natural disasters
·     Road Blockage
·     Instability at factory level due to workers vexation
·     Any unwanted situation beyond control
2.       Payment terms:
                                i.            50% advance in favor of Focus Engineering &Construction with the confirmed PO/work order
                              ii.            1st Running bill will be submit 20% based on work order value after completion of 50% works.
                            iii.            2nd Running bill will be submit 20% based on work order value after completion of 40% works
                             iv.            3rd running bill/Final bill will be submit 10% or above/lass as actual site measurement after completion of 100% work.
3.       Offer Submitted Excluding TAX & VAT
.




With Best Regard's

           

Md. Mahmudul Hasan Bhuiyan (Rana)
Managing Director
Focus Engineering & Construction
Cell: +8801818980727
Email: rana.bspi@yahoo.com